Taliaokeng Unit 2 pumping Station & Exit gate expansion work
Completed

Taliaokeng Unit 2 pumping Station & Exit gate expansion work

Owner: Water Resources Agency, MOEA
Amout: TWD 820,224,152
Scheduled Period: 720 days
Location: Xinzhuang Dist., New Taipei City
Yutian Pumping Station & diversion channel construction work
Completed

Yutian Pumping Station & diversion channel construction work

Owner: Water Resources Agency, MOEA
Amout: TWD 105,914,878
Scheduled Period: 300 days
Location: Jiaoxi Township, Yilan County
New construction for Shuwangpi Pumping station
Completed

New construction for Shuwangpi Pumping station

Owner: Water Resource Bureau of Taichung City Government
Amout: TWD 130,902,587
Scheduled Period: 470 days
Location: Wuri Dist, Taichung City